Work Profile Report : 17W395
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : E- File No. 52718
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
75.06
Resanction Cost :
75.06
Tentative Cost :
75.06
Exp. Upto Last Fy :
0.40
For CFY 2025-2026
Remaining :
74.66
Demand :
50.00
Allotment :
5.20
Exp in CFY :
5.20
Total Up to Date Exp :
5.60
Construction Started
Sanction on : 2 years 1 month ago
31 Jan 2024
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
30 %
Tentative Completion date on : 3 weeks 5 days from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पहाड़ कटान का कार्य प्रगति पर है -- as on 20-Feb-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: