Work Profile Report : 17W429
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : ई-पत्रावली संख्या 37533/2024 लोक निर्माण अनुभाग-2 देहरादून दिनांक 20-11-2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
194.44
Resanction Cost :
194.44
Tentative Cost :
161.40
Saving
33.04
Exp. Upto Last Fy :
3.12
For CFY 2025-2026
Remaining :
191.32
Demand :
146.50
Allotment :
106.33
Exp in CFY :
106.33
Total Up to Date Exp :
109.45
Construction Started
Sanction on : 1 year 3 months ago
20 Nov 2024
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
65 %
Tentative Completion date on : 1 day 3 hours from now
06 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर है | -- as on 20-Feb-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: