Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.5 | 3.5 | 3.500 | 0 | 0.000 | 0.000 |
18W591 :
Work not linked with IM
Bridges on The Basis of AI: RCC T BEAM MOTOR BRIDGE OVER BADI GAAD
Administrative Approval Detail : शा0सं0 4936(1)/।।।(2)/21-54(एम0एल0ए0)/2017 लोक निर्माण अनुभाग-2, देहरादून दिनाॅक 13-10-2021
TS Amount (lakhs) : 259.13 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
259.13
Resanction Cost :
259.13
Tentative Cost :
259.13
Exp. Upto Last Fy : 254.25
For CFY 2024-2025
Remaining : 4.88
Demand : 2.17
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 254.25
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 9 months ago
13 Oct 2021
Tentative Completion date:
1 year 3 months ago
31 Mar 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। नाबार्ड के अन्तर्गत मार्ग पंचवर्षीय अनुरक्षणाधीन है। -- as on 23-Apr-2024
Physical Peramenters