Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 1 | 1 | 0 | ||
Jobs | 1 | 1 | 1 | 0 |
18W779 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई-पत्रावली सं0 60145, लोक निर्माण अनुभाग-2, देहरादून दिनांक 22 नवम्बर, 2023
TS Amount (lakhs) : 4.32 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
4.32
Resanction Cost :
4.32
Tentative Cost :
4.32
Exp. Upto Last Fy : 0.10
For CFY 2024-2025
Remaining : 4.22
Demand : 3.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.10
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
7 months 3 weeks ago
22 Nov 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सर्वेक्षण कार्य प्रगति पर है। -- as on 23-Apr-2024
Physical Peramenters