Work Profile Report [18W779]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ई-पत्रावली सं0 60145, लोक निर्माण अनुभाग-2, देहरादून दिनांक 22 नवम्बर, 2023
TS Amount (lakhs) : 4.32 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
4.32
Resanction Cost :
4.32
Tentative Cost :
4.32
Exp. Upto Last Fy :
0.10
For CFY 2024-2025
Remaining :
4.22
Demand :
3.00
Allotment :
0.00
Exp in CFY :
1.10
Total Up to Date Exp :
1.20
Construction Started
Sanction on : 1 year 1 day ago
22 Nov 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
0 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
सर्वेक्षण कार्य प्रगति पर है। -- as on 23-Apr-2024