Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 0.000 | 2 | 2.000 | 0.000 |
18W803 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासन के ई पत्रावली संख्या- 19702, लोक निर्माण अनुभाग-2 देहरादून दिनांक 01 नवम्बर 2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
168.18
Resanction Cost :
168.18
Tentative Cost :
168.18
Exp. Upto Last Fy : 0.10
For CFY 2024-2025
Remaining : 168.08
Demand : 130.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.10
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 10 %
Sanction on :
8 months 2 weeks ago
01 Nov 2023
Tentative Completion date:
4 months 2 weeks from now
05 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सोलिंग का कार्य प्रगति पर। -- as on 26-Jun-2024
Physical Peramenters