Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 0.000 | 2 | 2.000 | 0.000 |
18W811 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई पत्रावली संख्या- 19207, लोक निर्माण अनुभाग-2, देहरादून दिनांक 07 फरवरी, 2024
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 78.93 Lacs
Resanction Cost : 78.93 Lacs
Exp. Upto Last Fy : 0.10 Lacs
For CFY 2024-2025
Remaining : 78.83 Lacs
Demand : 50.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.10 Lacs
in Tendering Stage
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
3 months 1 week ago
07 Feb 2024
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
निविदा स्वीकृति पत्र जारी अनुबन्ध गठन का कार्य प्रगति पर हैं -- as on 16-Mar-2024
Physical Peramenters