Work Profile Report [18W881]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ई- पत्रावली सं0 50206 लोक निर्माण अनुभाग-2 देहरादून दिनांक 5-11-2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
140.07
Resanction Cost :
140.07
Tentative Cost :
105.00
Saving
35.07
Exp. Upto Last Fy :
20.21
For CFY 2025-2026
Remaining :
119.86
Demand :
80.48
Allotment :
71.74
Exp in CFY :
71.74
Total Up to Date Exp :
91.95
Work completed
Sanction on : 1 year 2 months ago
05 Nov 2024
Physical Progress:
At start of FY 2025-2026 :
15 %
Up to Date :
100 %
Tentative Completion date on : 3 weeks 2 days ago
31 Dec 2025
Actual Completion Date : 3 weeks 2 days ago
31 Dec 2025
Physical Linear Components
Remark
कार्य पूर्ण। अनुरक्षण कार्य प्रगति पर है। -- as on 23-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: