Work Profile Report [19W302]

जनपद चम्पावत के विधानसभा के अन्तर्गत गोली-नदोला-अमकड़िया मोटर मार्ग एवं क्वैराला नदी में सेतु का निर्माण (प्रथम चरण)
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : 2086/।।।(2)/15-58(प्रा0आ0)/2013 दिनांक 26-03-2015

TS Amount (lakhs) : 75.9 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

75.90

Resanction Cost :

75.90

Tentative Cost :

75.90

Exp. Upto Last Fy :

0.02

For CFY 2025-2026

Remaining :

75.88

Demand :

5.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

0.02

Alignment Approved

Sanction on : 10 years 8 months ago

26 Mar 2015

Physical Progress:

At start of FY 2025-2026 :

10 %

Up to Date :

10 %

Tentative Completion date on : 3 years 8 months ago

31 Mar 2022

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
10
10
10
-
Bridge
2
2
2
-

Remark

view all

अधीक्षण अभियन्ता के पत्रांक 6181/387सी0 (याता0‘द’)-03/2025 दिनांक 28.08.2025 द्वारा समरेखण प्रस्ताव अनुमोदित।वन विभाग से संयुक्त निरीक्षण हेतु पत्र प्रेषित। -- as on 05-Dec-2025

Rating : 10

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: