Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 21.875 | 21.875 | 10.175 | 11.7 | 11.700 | 0.000 |
19W698 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E file no-35984
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 605.68 Lacs
Resanction Cost : 605.68 Lacs
Exp. Upto Last Fy : 378.46 Lacs
For CFY 2024-2025
Remaining : 227.22 Lacs
Demand : 227.22 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 378.46 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 76 %
Up to Date : 76 %
Sanction on :
9 months 2 weeks ago
31 Jul 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
BM & एस0डी0बी0सी0 व माइक्रो सरफेसिंग का कार्य पूर्ण, शेष कार्य प्रगति पर। -- as on 02-Apr-2024