Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 1 | 1 | 0 | ||
Span of Bridges [m] | 610 | 610 | 610 | 0 |
19W699 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E file no-35871
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 91.50 Lacs
Resanction Cost : 91.50 Lacs
Exp. Upto Last Fy : 36.00 Lacs
For CFY 2024-2025
Remaining : 55.50 Lacs
Demand : 30.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 36.00 Lacs
Survey work done
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
9 months 2 weeks ago
02 Aug 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सर्वेक्षण कार्य पूर्ण उपरान्त भू-तकनीकी जाॅंच गतिमान। -- as on 02-Apr-2024
Physical Peramenters