Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8.3 | 8.3 | 0.000 | 8.3 | 8.300 | 0.000 |
19W740 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : U.K. Govt. E File No. 31018 Date : 19-12-2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
473.34
Resanction Cost :
473.34
Tentative Cost :
473.34
Exp. Upto Last Fy : 12.29
For CFY 2024-2025
Remaining : 461.05
Demand : 461.05
Allotment : 0.00
Exp in CFY : 68.80
Total Up to Date Exp : 81.09
Construction Started
Physical Progress:
At start of FY 2024-2025 : 5 %
Up to Date : 30 %
Sanction on :
6 months 4 weeks ago
19 Dec 2023
Tentative Completion date:
7 months 3 weeks from now
14 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सिविल कार्य (दिवार स्कपर आदि ) प्रगति पर है -- as on 29-Jun-2024
Physical Peramenters