Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 18.67 | 18.67 | 0.000 | 18.67 | 0.000 | 0.000 |
19W741 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : U.K. Govt. E File No. 31018 Date : 19-12-2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
992.12
Resanction Cost :
992.12
Tentative Cost :
992.12
Exp. Upto Last Fy : 55.79
For CFY 2024-2025
Remaining : 936.33
Demand : 936.33
Allotment : 0.00
Exp in CFY : 134.55
Total Up to Date Exp : 190.33
Construction Started
Physical Progress:
At start of FY 2024-2025 : 5 %
Up to Date : 35 %
Sanction on :
6 months 4 weeks ago
19 Dec 2023
Tentative Completion date:
7 months 3 weeks from now
11 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
18.670 किमी के सापेक्ष 7.100 किमी में हॉटमिक्स का कार्य पूर्ण शेष लम्बाई में हॉटमिक्स व सिविल कार्य प्रगति पर है -- as on 29-Jun-2024
Physical Peramenters