Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 9.885 | 9.885 | 4.150 | 5.735 | 5.735 | 0.000 |
19W742 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : UK. Gov. E File No. 31805/55 Dated : 28-12-2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 326.19 Lacs
Resanction Cost : 326.19 Lacs
Exp. Upto Last Fy : 49.50 Lacs
For CFY 2024-2025
Remaining : 276.69 Lacs
Demand : 276.69 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 49.50 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 55 %
Up to Date : 80 %
Sanction on :
4 months 3 weeks ago
28 Dec 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 19-Mar-2024
Physical Peramenters