Work Profile Report [19W923]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E File No. 35871/2022 Dated ; 16-12-2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
958.34
Resanction Cost :
958.34
Tentative Cost :
958.34
Exp. Upto Last Fy :
124.27
For CFY 2025-2026
Remaining :
834.07
Demand :
769.00
Allotment :
55.95
Exp in CFY :
55.95
Total Up to Date Exp :
180.22
Construction Started
Sanction on : 7 months 3 weeks ago
16 Dec 2024
Physical Progress:
At start of FY 2025-2026 :
2 %
Up to Date :
25 %
Tentative Completion date on : 7 months 16 hours from now
09 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर है। -- as on 08-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: