Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.63 | 1.63 | 0.000 | 1.63 | 0.000 | 0.000 |
Jobs | 1 | 1 | 0 | 1 | 0 | 0 |
1W566 :
Work not linked with IM
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: Paththarkot Bridge
Administrative Approval Detail : 445/III(2)/21-51(MLA)/2017 TC
TS Amount (lakhs) : 135.21 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
135.21
Resanction Cost :
135.21
Tentative Cost :
135.21
Exp. Upto Last Fy : 105.73
For CFY 2024-2025
Remaining : 29.48
Demand : 5.00
Allotment : 5.00
Exp in CFY : 1.29
Total Up to Date Exp : 107.02
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 6 months ago
07 Jan 2022
Tentative Completion date:
1 year 1 month ago
25 May 2023
Actual Completion Date:
1 year 2 months ago
15 May 2023
Remark
Bottelneck: no issue
कार्य भौतिक रूप से पूर्ण, त्रिवर्षीय अनुरक्षण का कार्य किया जा रहा है | दायित्व शेष। -- as on 18-Jan-2024
Physical Peramenters