Work Profile Report : 1W767
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E - File No. 49007/2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
188.09
Resanction Cost :
188.09
Tentative Cost :
180.00
Saving
8.09
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
188.09
Demand :
90.00
Allotment :
31.15
Exp in CFY :
31.15
Total Up to Date Exp :
31.15
Construction Started
Sanction on : 1 year 3 days ago
29 Jan 2025
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
60 %
Tentative Completion date on : 5 months 3 weeks from now
27 Jul 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Work in progress. -- as on 16-Jan-2026
Assets :
Work not linked with IM