Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 10 | 10 | 3.550 | 6.45 | 0.450 | 0.000 |
20W35 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 सं0 2503/111 (2)/06 -37 (प्रा0आ0) /06 दि0 20/9/06
TS Amount (lakhs) : 178 Lacs
Financial Detail
Sanction Cost : 178.00 Lacs
Resanction Cost : 178.00 Lacs
Exp. Upto Last Fy : 134.52 Lacs
For CFY 2024-2025
Remaining : 43.48 Lacs
Demand : 25.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 134.52 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 70 %
Up to Date : 70 %
Sanction on :
17 years 7 months ago
20 Sep 2006
Tentative Completion date:
2 years 10 months from now
31 Mar 2027
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 11: AIP Division
Bottelneck: no issue
इस मार्ग की मूल स्वीकृति 10 किमी0 है। विस्तृत सर्वेक्षण के पश्चात मार्ग की वास्तविक लम्बाई 7.800 किमी0 है।
वास्तविक लम्बाई के सापेक्ष 3.550 किमी0 में मार्ग निर्माण कार्य पूर्ण कर लिया गया है। 0.450 किमी0 लम्बाई में कार्य प्रगति में है।
अवशेष 3.8 किमी0 लम्बाई में निर्माण कार्य हेतु पुनरीक्षित डी0पी0आर0 गठित की जा रही है।
-- as on 30-Mar-2024
Physical Peramenters