Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 7.5 | 7.5 | 1.000 | 6.5 | 2.500 | 0.000 |
20W39 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 सं0 764/111 (2)/ 08 -80 (प्रा0आ0) /07 दि0 24/3/08
TS Amount (lakhs) : 275.63 Lacs
Financial Detail
Sanction Cost : 275.63 Lacs
Resanction Cost : 275.63 Lacs
Exp. Upto Last Fy : 129.04 Lacs
For CFY 2024-2025
Remaining : 146.59 Lacs
Demand : 130.00 Lacs
Allotment : 20.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 129.04 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 50 %
Sanction on :
16 years 1 month ago
24 Mar 2008
Tentative Completion date:
9 months 1 week from now
02 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 17: AIP Govt of India
Bottelneck: no issue
4 किमी0 में पहाड़ कटान एवं 1 किमी0 में पार्ट -।। का कार्य पूर्ण ।
डी0एफ0ओ0 पिथौरागढ़ द्वारा किमी0 5 एवं 6 में आने वाले लगभग 62 से 63 पेड़ों के कटान को रोक दिया गया है। दि0 23.04.2024 को डी0एफ0ओ0 कार्यालय में उनसे वार्ता करने वर उनके द्वारा अवगत कराया गया कि सैद्धान्तिक स्वीकृति के उपरान्त 1 वर्ष में कार्य पूर्ण करने की स्वीकृति दी गई थी, वह समाप्त हो चुकी है। इसलिए कार्य को विधिवत स्वीकृति के उपरान्त ही कराया जाय। विधिवत स्वकृति अभी अप्राप्त है। दि0 24.04.2024 को भारत सरकार स्तर पर सम्पर्क किया गया, उनके द्वारा 2 विन्दुओं पर आपत्ति लगाई गई है। जिसका निराकरण किया जा रहा है।
-- as on 02-May-2024
Physical Peramenters