Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3.000 | 0 | 0.000 | 0.000 |
20W447 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 सं0 5633/।।। (2)/21-45 (एम0एल0ए0)/2017 दि0 17 नवम्बर 2021
TS Amount (lakhs) : 340.85 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
340.85
Resanction Cost :
340.85
Tentative Cost :
340.85
Exp. Upto Last Fy : 343.73
For CFY 2024-2025
Remaining : -2.88
Demand : 2.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 343.73
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 8 months ago
17 Nov 2021
Tentative Completion date:
9 months 2 weeks ago
30 Sep 2023
Actual Completion Date:
10 months 2 weeks ago
03 Sep 2023
Remark
Bottelneck: no issue
निर्माण कार्य पूर्ण । तीन वर्षीय अनुरक्षण का कार्य किया जा रहा है। -- as on 30-Mar-2024
Physical Peramenters