Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 2.500 | 2.5 | 2.500 | 0.000 |
20W449 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 सं0 424/।।।(2)/21.26(प्रा0आ0)/2017 दि0 05 जनवरी 2022
TS Amount (lakhs) : 266.16 Lacs
Financial Detail
Sanction Cost : 285.15 Lacs
Resanction Cost : 285.15 Lacs
Exp. Upto Last Fy : 138.85 Lacs
For CFY 2024-2025
Remaining : 146.30 Lacs
Demand : 140.00 Lacs
Allotment : 20.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 138.85 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 35 %
Up to Date : 60 %
Sanction on :
2 years 4 months ago
05 Jan 2022
Tentative Completion date:
1 week 1 day from now
28 May 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
मार्ग में कुल 5 किमी0 लम्बाई में बी0एम0 /एस0डी0बी0सी0 का कार्य किया जाना है, जिसे इस माह अनुबंध की निर्धारित तिथि दि0 25.05.2024 तक पूर्ण कर लिया जाएगा। -- as on 02-May-2024
Physical Peramenters