Work Profile Report [20W449]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0 सं0 424/।।।(2)/21.26(प्रा0आ0)/2017 दि0 05 जनवरी 2022
TS Amount (lakhs) : 266.16 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
284.15
Resanction Cost :
284.15
Tentative Cost :
284.15
Exp. Upto Last Fy :
138.85
For CFY 2024-2025
Remaining :
145.30
Demand :
119.00
Allotment :
130.00
Exp in CFY :
129.65
Total Up to Date Exp :
268.51
Construction Started
Sanction on : 2 years 10 months ago
05 Jan 2022
Physical Progress:
At start of FY 2024-2025 :
35 %
Up to Date :
100 %
Tentative Completion date on : 4 months 3 days ago
20 Jul 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण । -- as on 04-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: