Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 2.500 | 2.5 | 2.500 | 2.500 |
20W449 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 सं0 424/।।।(2)/21.26(प्रा0आ0)/2017 दि0 05 जनवरी 2022
TS Amount (lakhs) : 266.16 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
284.15
Resanction Cost :
284.15
Tentative Cost :
284.15
Exp. Upto Last Fy : 138.85
For CFY 2024-2025
Remaining : 145.30
Demand : 140.00
Allotment : 130.00
Exp in CFY : 105.85
Total Up to Date Exp : 244.71
Construction Started
Physical Progress:
At start of FY 2024-2025 : 35 %
Up to Date : 95 %
Sanction on :
2 years 6 months ago
05 Jan 2022
Tentative Completion date:
2 days 18 hours from now
20 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
BM and SDBC का कार्य पूर्ण । -- as on 26-Jun-2024
Physical Peramenters