Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Buildings | 1 | 1 | 0 | 1 | 0 | 0 |
20W533 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E file N0- 55281/XXXVI(2)/23/8-budget/2023 dt- 06.06.2023
TS Amount (lakhs) : 443.88 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
477.50
Resanction Cost :
477.50
Tentative Cost :
477.50
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 477.50
Demand : 225.00
Allotment : 125.00
Exp in CFY : 30.84
Total Up to Date Exp : 30.84
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 5 %
Sanction on :
1 year 1 month ago
29 May 2023
Tentative Completion date:
1 year 3 months from now
14 Nov 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
दि0 15.03.2024 द्वारा अनुबंध गठित। भवन का स्थल विकास का कार्य प्रगति पर है। स्थल विकास के पश्चात् मुख्य भवन का कार्य कराया जायेगा। स्थल विकास का कार्य माह मई में पूर्ण किया जा सकेगा। वर्तमान में रिटेनिग वाल तथा समतलीकरण का कार्य प्रगति में है। स्थल पर 7 से 8 देवदार के वृक्ष आ रहे है। जिसके लिए मा0 जिला न्यायाधीश पिथौरागढ़ द्वारा इन वृक्षों का रिप्लांटेशन हेतु निर्देशित किया गया है। दि0 30.12.2023 द्वारा उक्त देवदार के वृक्षों का रिप्लांटेशन हेतु वन क्षेत्राधिकारी गंगोलीहाट को पत्र लिख गया था। वन क्षेत्राधिकारी गंगोलीहाट द्वारा अवगत कराया गया है कि इन वृक्षों के अन्यत्र प्लांटेशन किए जाने पर जीवित रहने की कोई सम्भावना नही है। अतः वृक्षों के पातन के अलावा कोई विकल्प नही है। दि0 08.04.2024 द्वारा वन क्षेत्राधिकारी गंगोलीहाट को उक्त देवदार के वृक्षों को कार्य स्थल से हटाने हेतु अनुरोध प्रेषित किया गया है। दि0 24.05.2024 को मा0 उच्च न्यायालय नैनीताल के न्यायमूर्ति पुरोहित साहब द्वारा स्थलीय निरीक्षण किया गया, जिसमें उनके द्वारा पेंड़ों को बचाने का प्रयास किए जाने हेतु कहा गया है। -- as on 10-Jun-2024
Physical Peramenters