Work Profile Report [20W550]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : शासनादेश ई0 फाइल संख्या 51659 दि0 13.12.2023
TS Amount (lakhs) : 512.56 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
512.56
Resanction Cost :
512.56
Tentative Cost :
512.56
Exp. Upto Last Fy :
278.73
For CFY 2025-2026
Remaining :
233.83
Demand :
202.28
Allotment :
210.00
Exp in CFY :
202.28
Total Up to Date Exp :
481.01
In Maintenance After Completion
Sanction on : 2 years 2 days ago
13 Dec 2023
Physical Progress:
At start of FY 2025-2026 :
40 %
Up to Date :
100 %
Tentative Completion date on : 5 months 2 weeks ago
30 Jun 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण । 3 वर्षीय अनुरक्षण का कार्य किया जा रहा है. -- as on 15-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: