Work Profile Report [20W556]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : उत्तराखण्ड शासन लोक निर्माण अनुभाग -2 के ई0 फाईल संख्या -51659 दि0 14.03.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
210.47
Resanction Cost :
210.47
Tentative Cost :
210.47
Exp. Upto Last Fy :
20.39
For CFY 2025-2026
Remaining :
190.08
Demand :
182.00
Allotment :
75.05
Exp in CFY :
74.62
Total Up to Date Exp :
95.01
Construction Started
Sanction on : 1 year 10 months ago
14 Mar 2024
Physical Progress:
At start of FY 2025-2026 :
20 %
Up to Date :
40 %
Tentative Completion date on : 8 months 3 weeks from now
15 Oct 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
2.5 किमी0 में पहाड़ कटान का कार्य पूर्ण। शेष प्रगति में है. -- as on 29-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: