Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 10 | 10 | 0.000 | 10 | 0.000 | 0.000 |
20W84 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 सं0 5150/111(2)/10 -18 (प्रा0आ0) /2010 दि0 16/8/10
TS Amount (lakhs) : 5.41 Lacs
Financial Detail
Sanction Cost : 126.00 Lacs
Resanction Cost : 126.00 Lacs
Exp. Upto Last Fy : 1.00 Lacs
For CFY 2024-2025
Remaining : 125.00 Lacs
Demand : 10.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 1.00 Lacs
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
13 years 9 months ago
16 Aug 2010
Tentative Completion date:
2 years 5 months from now
31 Oct 2026
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 12: AIP DM
Bottelneck: no issue
सैैद्धान्तिक स्वीकृति की अनुपालन आख्या दि0 07-04-2021 को नोडल अधिकारी देहरादून को प्रेषित। इस कार्यालय के पत्राॅक 836/27सी दि0 12-05-2023 एवं पत्राॅक 1351/27 सी दि0 05-08-2023 द्वारा क्षतिपूति वृक्षारोपण का प्रस्ताव तैयार करने हेतु पुनः उपजिलाधिकारी बेरीनाग से अनुरोध किया गया है। उपजिलाधिकारी बेरीनाग के पत्राॅक 825/क्षति0वृक्षा0 /रा0का0 /2023-24 दि0 22-09-2023 को क्षतिपूर्ति वृक्षारोपड़ का प्रस्ताव जिलाधिकारी पिथौरागढ़ को प्रेषित है। दि0 26-04-2024 को प्रस्ताव आपत्ति में प्राप्त प्रस्ताव उपजिलाधिकारी के माध्यम से प्रेषित किया जाना है। जिलाधिकारी पिथौरागढ़ के पत्रांक 295/सात-भू0ह0/2022-23 दि0 06.05.2024 को प्रस्ताव 3 विन्दुओं में आपत्ति में प्राप्त । दि0 07.05.2024 को उपजिलाधिकारी कार्यालय में सम्पर्क कर लिया गया है। उनके द्वारा अवगत कराया गया है कि शीघ्र ही जिलाधिकारी महोदय को प्रस्ताव प्रेषित कर देंगे । -- as on 17-May-2024
Physical Peramenters