Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 0.000 | 3 | 0.000 | 0.000 |
20W89 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 1440/।।। (2)/11-8 (प्रा0आ0)/ 2010 दि0 28/03/11
TS Amount (lakhs) : 3 Lacs
Financial Detail
Sanction Cost : 37.80 Lacs
Resanction Cost : 37.80 Lacs
Exp. Upto Last Fy : 0.09 Lacs
For CFY 2024-2025
Remaining : 37.71 Lacs
Demand : 10.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.09 Lacs
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
13 years 1 month ago
28 Mar 2011
Tentative Completion date:
2 years 5 months from now
01 Nov 2026
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सैद्धान्तिक स्वीकृति 2/2019 में प्राप्त। दि्वतीय चरण की डी0पी0आर0 स्वीकृत । नाप भूमि का मुआवजे का भुगतान मार्ग निर्माण के दौरान किया जायेगा। -- as on 04-Jul-2021
Physical Peramenters