22W1448 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 5347/III(2)/2023-01(प्रा०आ०)/2023
TS Amount (lakhs) : 82.25 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
95.00
Resanction Cost :
95.00
Tentative Cost :
95.00
Exp. Upto Last Fy : 18.42
For CFY 2024-2025
Remaining : 76.58
Demand : 76.58
Allotment : 12.00
Exp in CFY : 11.78
Total Up to Date Exp : 30.20
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 30 %
Sanction on :
7 months 1 week ago
05 Dec 2023
Tentative Completion date:
3 months 1 week from now
28 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर | -- as on 30-Apr-2024