Work Profile Report [22W1574]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : E file no. 51385/59, dt. 27.01.2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
256.18
Resanction Cost :
256.18
Tentative Cost :
256.18
Exp. Upto Last Fy :
10.79
For CFY 2025-2026
Remaining :
245.39
Demand :
20.00
Allotment :
1.27
Exp in CFY :
1.27
Total Up to Date Exp :
12.06
Construction Started
Sanction on : 10 months 2 weeks ago
27 Jan 2025
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
15 %
Tentative Completion date on : 11 months 2 weeks from now
30 Nov 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
जल निगम द्वारा सीवर लाईन का कार्य किया जा रहा है। जिस कारण कार्य बाधित है। -- as on 11-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© 2025 PWD Uttarakhand