Work Profile Report : 22W1669
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : E-File No.- 47985/60, dt. 04.08.2025
TS Amount (lakhs) : 319.2 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
319.20
Resanction Cost :
319.20
Tentative Cost :
319.20
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
319.20
Demand :
100.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Construction Started
Sanction on : 7 months 21 hours ago
04 Aug 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
15 %
Tentative Completion date on : 5 months 3 weeks from now
31 Aug 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
बायीं ओर के एबटमेन्ट के आर0सी0सी0 राफट की कार्य पूर्ण। -- as on 13-Feb-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: