Work Profile Report [23W1151]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : G.O. no.- I/103650/2023 e-file no.- 43713
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
34.12
Resanction Cost :
34.12
Tentative Cost :
34.02
Saving
0.10
Exp. Upto Last Fy :
0.10
For CFY 2025-2026
Remaining :
34.02
Demand :
27.80
Allotment :
4.08
Exp in CFY :
4.08
Total Up to Date Exp :
4.18
Construction Started
Sanction on : 2 years 10 months ago
02 Mar 2023
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
65 %
Tentative Completion date on : 7 months 1 week from now
31 Aug 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 15-Jan-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: