Work Profile Report [23W1277]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : G.O. no.- I/270758/2025, e-file no.- 51571
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
201.58
Resanction Cost :
201.58
Tentative Cost :
201.58
Exp. Upto Last Fy :
0.10
For CFY 2025-2026
Remaining :
201.48
Demand :
194.91
Allotment :
51.87
Exp in CFY :
51.87
Total Up to Date Exp :
51.97
Construction Started
Sanction on : 9 months 1 week ago
27 Jan 2025
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
25 %
Tentative Completion date on : 5 months 2 weeks from now
18 Apr 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 09-Oct-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© 2025 PWD Uttarakhand