Work Profile Report [24W1066]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासन का ई पत्रावली संख्या 60173 लो0 नि0 अनुभाग -2 देहरादून दिनांक 27-03-2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
90.00
Resanction Cost :
90.00
Tentative Cost :
90.00
Exp. Upto Last Fy :
0.10
For CFY 2025-2026
Remaining :
89.90
Demand :
63.00
Allotment :
7.32
Exp in CFY :
7.32
Total Up to Date Exp :
7.42
Construction Started
Sanction on : 4 months 1 week ago
27 Mar 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
35 %
Tentative Completion date on : 4 months 6 days from now
15 Dec 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
तटबन्ध, का कार्य पूर्ण। जी0एस0बी0, का कार्य प्रगति पर है। -- as on 09-Jul-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand