Work Profile Report [24W1067]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : शासन का ई पत्रावली संख्या 58805 लो0 नि0 अनुभाग -2 देहरादून दिनांक 14-05-2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
101.05
Resanction Cost :
101.05
Tentative Cost :
101.05
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
101.05
Demand :
60.52
Allotment :
16.52
Exp in CFY :
16.52
Total Up to Date Exp :
16.52
Construction Started
Sanction on : 7 months 2 weeks ago
14 May 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
50 %
Tentative Completion date on : 6 months 1 week from now
15 Jul 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
जी0एस0बी0, जी0-2 का कार्य पूर्ण। जी-3 एवं क्रास ड्रेनेज का कार्य प्रगति में। -- as on 02-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: