Work Profile Report [24W756]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश संख्या 136/।।।(2)/20-29(प्रा0आ0) /2018 दिनांक 01-02-2021
TS Amount (lakhs) : 581.01 Lacs
Budget Financial Head : TSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
581.04
Resanction Cost :
581.04
Tentative Cost :
30.46
Saving
550.58
Exp. Upto Last Fy :
33.51
For CFY 2025-2026
Remaining :
547.53
Demand :
0.10
Allotment :
55.18
Exp in CFY :
55.18
Total Up to Date Exp :
88.69
Construction Started
Sanction on : 4 years 9 months ago
01 Feb 2021
Physical Progress:
At start of FY 2025-2026 :
5 %
Up to Date :
25 %
Tentative Completion date on : 1 year 1 month from now
31 Dec 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पीयर्स एवं एबटमेन्ट कार्य प्रगति में। -- as on 24-Oct-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: