Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.24 | 3.24 | 0.000 | 3.24 | 3.240 | 0.000 |
No of Bridges | 1 | 1 | 0 | 1 | 1 | 0 |
Span of Bridges [m] | 60 | 60 | 0.000 | 60 | 60.000 | 0.000 |
24W756 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 136/।।।(2)/20-29(प्रा0आ0) /2018 दिनांक 01-02-2021
TS Amount (lakhs) : 581.01 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
581.04
Resanction Cost :
581.04
Tentative Cost :
581.04
Exp. Upto Last Fy : 30.46
For CFY 2024-2025
Remaining : 550.58
Demand : 250.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 30.46
Construction Started
Physical Progress:
At start of FY 2024-2025 : 15 %
Up to Date : 15 %
Sanction on :
3 years 5 months ago
01 Feb 2021
Tentative Completion date:
11 months 2 days ago
15 Aug 2023
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 17: AIP Govt of India
Bottelneck: Long Term Forest Approval
ए-1 पर 01 न0 वैल फाउन्डेशन का कार्य पूर्ण। ए-2 पर वैल फाउन्डेशन का कार्य प्रगति पर है। वन भूमि के कारण कार्य बाधित रहा। वर्तमन के सैद्धान्तिक स्वीकृति पाप्त हो चुकी है। सैद्धान्तिक स्वीकृति में प्रदत्त शर्तों की अनुपालन आख्या प्रभागीय वनाधिकारी तराई पूर्वी वन प्रभाग हल्द्वानी ने अपने पत्रांक 6603/12-1 हल्द्वानी दिनांक 10-05-2024 द्वारा वनभूमि हस्तान्तरण प्रस्ताव वन संरक्षक पश्चिमी वृत्त उत्तराखण्ड हल्द्वानी को प्रेषित कर दिया गया है। -- as on 16-May-2024
Physical Peramenters