Work Profile Report [24W767]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश संख्या 935/।।।(2) /21-70 (एम0एल0ए0) /2017 टी0सी0 - ।। दिनांक 30-03-2021
TS Amount (lakhs) : 98.43 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
98.43
Resanction Cost :
91.95
Tentative Cost :
91.95
Exp. Upto Last Fy :
85.43
For CFY 2025-2026
Remaining :
6.52
Demand :
3.00
Allotment :
3.00
Exp in CFY :
3.00
Total Up to Date Exp :
88.43
In Maintenance After Completion
Sanction on : 4 years 9 months ago
30 Mar 2021
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 3 years 5 months ago
10 Jul 2022
Actual Completion Date : 3 years 5 months ago
10 Jul 2022
Physical Linear Components
Remark
Overall Saving 6.48 has been recorded as expected cost of work reduced from 98.43 to 91.95 . -- as on 18-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: