Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.225 | 0.225 | 0.000 | 0.225 | 0.225 | 0.000 |
25W1131 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : स्टेट इन्फ्रास्ट्रक्चर एण्ड इण्डस्ट्रीयल डेवलपमेन्ट कारपोरेशन आॅफ उत्तराखण्ड देहरादून (सिडकुल) का पत्रांक 655/उ0म0प्र0(वा0)/सिडकुल/2023 दि0 06.07.2023
TS Amount (lakhs) : 52.92 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
52.92
Resanction Cost :
52.92
Tentative Cost :
52.92
Exp. Upto Last Fy : 15.79
For CFY 2024-2025
Remaining : 37.13
Demand : 37.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 15.79
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
1 year 1 week ago
06 Jul 2023
Tentative Completion date:
2 months 1 week from now
30 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
टाप कोट का कार्य पूर्ण शेष कार्य प्रगति में -- as on 11-Apr-2024
Physical Peramenters