Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.69 | 4.69 | 0.000 | 4.69 | 4.690 | 0.000 |
25W1151 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 । /41260 /2023 (ई0 फाईल सं0 56071) दि0 23.07.2023
TS Amount (lakhs) : 249.19 Lacs
Financial Detail
Sanction Cost : 249.19 Lacs
Resanction Cost : 249.19 Lacs
Exp. Upto Last Fy : 157.29 Lacs
For CFY 2024-2025
Remaining : 91.90 Lacs
Demand : 50.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 157.29 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 70 %
Up to Date : 70 %
Sanction on :
9 months 3 weeks ago
23 Jul 2023
Tentative Completion date:
3 months 4 days from now
24 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
डब्लू0एम0एम0 का कार्य पूर्ण, शेष कार्य प्रगति में। -- as on 06-Mar-2024
Physical Peramenters