Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.6 | 2.6 | 0.000 | 2.6 | 0.000 | 0.000 |
25W1175 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 । /183608 /2024 (ई0 फाईल सं0 50220) दि0 22.01.2024
TS Amount (lakhs) : 144.75 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
144.75
Resanction Cost :
144.75
Tentative Cost :
144.75
Exp. Upto Last Fy : 53.68
For CFY 2024-2025
Remaining : 91.07
Demand : 85.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 53.68
Construction Started
Physical Progress:
At start of FY 2024-2025 : 70 %
Up to Date : 70 %
Sanction on :
5 months 3 weeks ago
22 Jan 2024
Tentative Completion date:
4 months 5 days from now
23 Nov 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
टाप कोट का कार्य पूर्ण, शेष कार्य प्रगति में -- as on 27-Jun-2024
Physical Peramenters