Work Profile Report [25W1175]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 । /183608 /2024 (ई0 फाईल सं0 50220) दि0 22.01.2024
TS Amount (lakhs) : 144.75 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
144.75
Resanction Cost :
144.75
Tentative Cost :
141.50
Saving
3.25
Exp. Upto Last Fy :
53.68
For CFY 2024-2025
Remaining :
91.07
Demand :
85.00
Allotment :
40.00
Exp in CFY :
35.02
Total Up to Date Exp :
88.70
Construction Started
Sanction on : 10 months 1 day ago
22 Jan 2024
Physical Progress:
At start of FY 2024-2025 :
70 %
Up to Date :
75 %
Tentative Completion date on : 3 months 2 weeks from now
10 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
टाप कोट का कार्य पूर्ण, शेष कार्य प्रगति में -- as on 29-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: