Work Profile Report [25W1207]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 ।/259168/2024 (ई0 फाईल सं0 67240) दि0 06.12.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
367.10
Resanction Cost :
367.10
Tentative Cost :
367.10
Exp. Upto Last Fy :
0.10
For CFY 2025-2026
Remaining :
367.00
Demand :
367.00
Allotment :
69.07
Exp in CFY :
69.07
Total Up to Date Exp :
69.17
Construction Started
Sanction on : 8 months 3 weeks ago
06 Dec 2024
Physical Progress:
At start of FY 2025-2026 :
5 %
Up to Date :
50 %
Tentative Completion date on : 7 months 2 weeks from now
19 Apr 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
डब्लू0एम0एम0 का कार्य पूर्ण, शेष कार्य प्रगति में -- as on 23-Aug-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand