Work Profile Report [25W1227]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : शा0सं0 656/।।।(2) /25-63 (एम0एल0ए0) /2022 दि0 23.04.2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
1013.94
Resanction Cost :
1013.94
Tentative Cost :
1013.94
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
1,013.94
Demand :
754.08
Allotment :
463.12
Exp in CFY :
463.12
Total Up to Date Exp :
463.12
Construction Started
Sanction on : 9 months 7 hours ago
23 Apr 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
45 %
Tentative Completion date on : 10 months 2 weeks from now
11 Dec 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
5.00 किमी0 में डी0बी0एम0 का कार्य पूर्ण, शेष कार्य प्रगति में -- as on 14-Jan-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: