Work Profile Report [25W1240]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : शा0सं0 ।/327111/2025 (ई0 फाईल सं0 66717) दि0 02.09.2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
67.99
Resanction Cost :
67.99
Tentative Cost :
67.99
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
67.99
Demand :
12.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Construction Started
Sanction on : 4 months 3 weeks ago
02 Sep 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
15 %
Tentative Completion date on : 8 months 3 weeks from now
14 Oct 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
नाली एवं इण्टर कोट का कार्य प्रगति में -- as on 14-Jan-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: