Work Profile Report : 25W1243
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : शा0सं0 ।/327112/2025 (ई0 फाईल सं0 68062) दि0 02.09.2025
TS Amount (lakhs) : 70.55 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
70.55
Resanction Cost :
70.55
Tentative Cost :
70.55
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
70.55
Demand :
26.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Construction Started
Sanction on : 5 months 1 week ago
02 Sep 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
70 %
Tentative Completion date on : 8 months 1 week from now
20 Oct 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
टाप कोट का कार्य पूर्ण, शेष कार्य प्रगति में। -- as on 28-Jan-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: