Work Profile Report [2W256]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 148/।।।(2)/16-59(प्रा.आ.)/2015 दि0 13.01.2016
TS Amount (lakhs) : 190.36 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
404.30
Resanction Cost :
404.30
Tentative Cost :
404.30
Exp. Upto Last Fy :
92.27
For CFY 2025-2026
Remaining :
312.03
Demand :
15.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
92.27
Construction Started
Sanction on : 9 years 6 months ago
13 Jan 2016
Physical Progress:
At start of FY 2025-2026 :
35 %
Up to Date :
50 %
Tentative Completion date on : 3 weeks 1 day ago
17 Jul 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
7.00 किमी0 पहाड़ कटान का कार्य पूर्ण। मुआवजा वितरण की कार्यवाही गतिमान। -- as on 17-Jul-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: