Work Profile Report [2W300]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 2008/।।।(2)/16-53(एम.एल.ए.)/2015 दि0 27.06.2016
TS Amount (lakhs) : 155.91 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
315.84
Resanction Cost :
315.84
Tentative Cost :
315.84
Exp. Upto Last Fy :
164.61
For CFY 2025-2026
Remaining :
151.23
Demand :
10.00
Allotment :
0.25
Exp in CFY :
0.25
Total Up to Date Exp :
164.86
Construction Started
Sanction on : 9 years 1 month ago
27 Jun 2016
Physical Progress:
At start of FY 2025-2026 :
45 %
Up to Date :
50 %
Tentative Completion date on : 4 months 3 weeks from now
30 Dec 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पहाड़ कटान का कार्य पूर्ण। मुआवजा वितरण की कार्यवाही गतिमान। -- as on 17-Jul-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand