Work Profile Report [2W306]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 2103/।।।(2)/16-52(एम.एल.ए.) /2015 दि0 11.07.2016
TS Amount (lakhs) : 189.35 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
189.35
Resanction Cost :
189.35
Tentative Cost :
189.35
Exp. Upto Last Fy :
67.25
For CFY 2025-2026
Remaining :
122.10
Demand :
20.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
67.25
Construction Started
Sanction on : 9 years 4 weeks ago
11 Jul 2016
Physical Progress:
At start of FY 2025-2026 :
30 %
Up to Date :
30 %
Tentative Completion date on : 4 months 1 week from now
20 Dec 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
विवाद के कारण कार्य बाधित। विवाद सुलझा लिया गया है। कार्य माह दिसम्बर 2025 तक पूर्ण करा लिया जायेगा। -- as on 07-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: