Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 5.000 | 0.000 |
2W518 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 436/।।।(2)/21-48(एम0एल0ए0)/2017टी.सी. दि0 06.01.2022
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 286.93 Lacs
Resanction Cost : 286.93 Lacs
Exp. Upto Last Fy : 191.73 Lacs
For CFY 2024-2025
Remaining : 95.20 Lacs
Demand : 72.00 Lacs
Allotment : 50.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 191.73 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 49 %
Up to Date : 79 %
Sanction on :
2 years 4 months ago
06 Jan 2022
Tentative Completion date:
2 weeks 53 seconds from now
02 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
5.00 किमी0 लमबाई में सोलिंग,इण्टरकोट व टापकोट का कार्य का कार्य पूर्ण। 3.00 Km. पी सी का कार्य पूर्ण 2.00 Km.प्रगति पर। -- as on 16-May-2024
Physical Peramenters