Work Profile Report [2W518]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 436/।।।(2)/21-48(एम0एल0ए0)/2017टी.सी. दि0 06.01.2022
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
286.93
Resanction Cost :
286.93
Tentative Cost :
286.93
Exp. Upto Last Fy :
191.73
For CFY 2024-2025
Remaining :
95.20
Demand :
72.00
Allotment :
50.00
Exp in CFY :
63.32
Total Up to Date Exp :
255.05
In Maintenance After Completion
Sanction on : 2 years 10 months ago
06 Jan 2022
Physical Progress:
At start of FY 2024-2025 :
49 %
Up to Date :
100 %
Tentative Completion date on : 5 months 3 weeks ago
01 Jun 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण । -- as on 08-Nov-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: