Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 0.000 | 0.000 |
2W674 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : Efile No. 56806/53 Dt. 23/02/2024
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 310.33 Lacs
Resanction Cost : 310.33 Lacs
Exp. Upto Last Fy : 0.10 Lacs
For CFY 2024-2025
Remaining : 310.23 Lacs
Demand : 30.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.10 Lacs
in Tendering Stage
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
2 months 3 weeks ago
23 Feb 2024
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
निविदा आमंत्रित। -- as on 25-Feb-2024
Physical Peramenters