Work Profile Report [2W674]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : Efile No. 56806/53 Dt. 23/02/2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
310.33
Resanction Cost :
310.33
Tentative Cost :
310.33
Exp. Upto Last Fy :
0.10
For CFY 2024-2025
Remaining :
310.23
Demand :
55.00
Allotment :
58.97
Exp in CFY :
58.97
Total Up to Date Exp :
59.07
Construction Started
Sanction on : 10 months 1 day ago
23 Feb 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
10 %
Tentative Completion date on : 10 months 1 week from now
01 Nov 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
दीवारों एवं स्कपर का कार्य प्रगति पर। -- as on 06-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: