Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3.000 | 0 | 0.000 | 0.000 |
30W1111 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 1640(ए)/।।।(2)/18-02 (एम0एल0ए0)/2017 दि0 24-04-18
TS Amount (lakhs) : 54.57 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
54.57
Resanction Cost :
54.57
Tentative Cost :
54.57
Exp. Upto Last Fy : 20.82
For CFY 2024-2025
Remaining : 33.75
Demand : 15.00
Allotment : 5.00
Exp in CFY : 3.18
Total Up to Date Exp : 24.00
Construction Started
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 90 %
Sanction on :
6 years 2 months ago
24 Apr 2018
Tentative Completion date:
8 months 2 weeks ago
31 Oct 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
समरेखण स्वीकृत। पिलरों का कार्य गतिमान है तथा द्वितीय चरण की डी0पी0आर0 गठित कर मुख्य अभियन्ता (ग0क्षे0) लो0नि0वि0, पौड़ी के पत्रसं0- 1288/6(110)याता0-पौड़ी/20 दि0 10-03-21 द्वारा रू0 64.28 लाख मात्र का ़िद्वतीय चरण (स्टेज-।) का आगणन प्रमुख सचिव, लो0नि0 अनुभाग- 2 उत्तराखण्ड शासन, देहरादून को पे्रषित। द्वितीय चरण (स्टेज-।) लागत रू0 62.70 लाख की स्वीकृति प्राप्त। कार्य प्रगति पर है। -- as on 23-Jul-2022
Physical Peramenters