Work Profile Report [30W1153]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0- 1291(4)/।।।(2)/19-02 (एम0एल0ए0)/17 टी0सी0 दि0 08-03-19
TS Amount (lakhs) : 210.62 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
210.62
Resanction Cost :
221.20
Tentative Cost :
221.20
Exp. Upto Last Fy :
222.11
For CFY 2024-2025
Remaining :
-0.91
Demand :
3.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
222.11
In Maintenance After Completion
Sanction on : 5 years 8 months ago
08 Mar 2019
Physical Progress:
At start of FY 2024-2025 :
90 %
Up to Date :
90 %
Tentative Completion date on : 2 years 7 months ago
31 Mar 2022
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Excess requirement 10.58 has been counted as tentative cost increased from 210.62 to 221.20 . -- as on 16-Oct-2024
Assets :