Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 5.000 | 0.000 |
30W1364 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 6588/।।।(2)/21-02 (एम0एल0ए0)/2017 टी0सी0
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 43.50 Lacs
Resanction Cost : 43.50 Lacs
Exp. Upto Last Fy : 2.71 Lacs
For CFY 2024-2025
Remaining : 40.79 Lacs
Demand : 1.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 2.71 Lacs
Survey work done
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 10 %
Sanction on :
2 years 4 months ago
31 Dec 2021
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सर्वेक्षण का कार्य पूर्ण। समरेखण प्रस्ताव गठित कर अधीक्षण अभियन्ता, छठा वृत्त, लो0नि0वि0, उत्तरकाशी को पे्रषित। -- as on 01-Mar-2024
Physical Peramenters