Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 0.000 | 3 | 3.000 | 0.000 |
30W1446 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 1/106279/2023 and E File No. 31503
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
4.50
Resanction Cost :
4.50
Tentative Cost :
4.50
Exp. Upto Last Fy : 0.20
For CFY 2024-2025
Remaining : 4.30
Demand : 1.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.20
Survey work done
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 40 %
Sanction on :
1 year 4 months ago
15 Mar 2023
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
समरेखण स्वीकृत।संयुक्त निरीक्षण हेतु इस कार्यालय के पत्रांक 751/वनभूमि दिनांक 03.05.2024 द्वारा डी. फ. ओ. को पत्र प्रेषित -- as on 04-May-2024
Physical Peramenters